- 35,864
- Downtown North Dakota
- Cy-Fi
This is my cue to jump in. I am the CAD Manager for an Electrical Engineer. Currently, we are putting most of our efforts into getting this out. It is our fourth Scheels building this year alone, all of which are similar, but vary (some are new construction, others remodeled Target stores, etc.), not to mention all of the "little" projects (in terms of size, not importance, right?) we have worked and are working on. With that out of the way, believe me when I tell you this - when I get updated plans sent to me, within the hour they are cleaned up, stripped down and in circulation. Maybe not necessarily XREF'd into the drawings, but we have a system for that, as well....fix all the coordination mistakes made by the engineers, where ductwork runs through light fixtures and there's no room for a sprinkler head (even though the mechanical and electrical engineer sit directly across from each other), and you'll need at least 48 hours to get the engineers to stop using the old version and update to the current floor plan (which was given to them 2 weeks ago when you thought it was final).
When working on a different Scheels project last year, a few of us were here at 3am to beat the noon deadline (because we had just received mechanical plans earlier that day and there were *goes to check* 181 heat pumps, not to mention AHU's, exhaust fans, etc. All told, 253 motors placed, wired and circuited in less than 24 hours while doing all of the other last minute drawing cleanups). It still dumbfounds me that we (Architectural and Electrical) can be so far along in the design and Mechanical is barely, or more accurately hasn't, started on design a week before the due date.
I just told one of the Engineers here about what I had written above and was relayed a story: An architect moved an exterior wall out a few feet. This required the Mechanical to up-size the AHU to accommodate the extra space. This required us to up-size the Switchgear to handle the larger AHU which required the room in which said Switchgear was located to be enlarged.
It is indeed a vicious cycle, but in the age of "I want it done yesterday" we just aren't given the time to go over the drawings as thoroughly as was the norm even 10 years ago.
Just as a point of interest, at least from my standpoint, at any given point, I am working on at least 3 and typically 6+ different projects a day. My time sheet get a bit messy most weeks.